PREPARATION AT GANIL, TESTS OF MECHANICS AND DETECTORS
3rd week of December 2009: mounting of the mechanical configurations for BigRIPs and RIPS
(Jean-François LIBIN, Patrice GANGNANT, Emmanuel RINDEL, Philippe ROSIER).
2010
January
2nd week: mounting of the mechanics for thin Si detectors of the RIPS configuration.
3rd week: Tests of the merge between RIKEN and GANIL Data Acquisition systems.
(H. BABA, CH. HOUARNER, C. MAUGEAIS, B. RAINE, F. SAILLANT).
BigRIPS configuration mounted with 6 telescopes. Tests of the telescopes, MUVI cards.
Tests with an Alpha source.
BigRIPS configuration is ready.
4th week: Tests of the 6 telescopes, tests of the spare electronics.
Tests of the equipment to be sent to RIKEN.
Tests of the Mufee cards and additional MUST2 Si-strip detectors needed for the RIPS configuration.
February
From 8th: packaging, list of every element to be sent, storage in SPEG area, volume and weight estimates,
The 4 boxes needed for the transportation by air-plane were built from 9th till 28th.
March
Monday 1st -Tuesday 2nd: boxes at GANIL, packaging of the equipment.
Thrusday 4TH March: the 4 wooden boxes (1852kg in total) are loaded on the truck going to Roissy.
4TH MARCH: BOXES AT ROISSY -CDG AIRPORT.
Storage….
10TH MARCH: DEPARTURE TO JAPAN.